Verified Field Deliveries

Industrial Automation Project Case Studies

Each case study is anonymised—protecting customer proprietary intellectual property, production volumes, and internal details—while describing the real technical coordination challenges, engineering actions, and verified outcomes.

0.4%
AOI vision false-reject rate achieved down from 7.8%
-2.9s
Cycle time shaved per part on high-speed indexing assembly line
100%
MES serialized part traceability verified over 10,000 continuous test units
6 Days
SAT punch-list resolved to sign-off after 3 weeks of vendor impasse

Featured Case Studies

Verified Delivery

AOI Vision System Commissioning & False Reject Reduction

Context: Automated Optical Inspection cell deployed on a high-speed packaging and surface inspection line.

Challenge: System flagged an unacceptably high 7.8% false defect rate due to ambient daylight shifts and reflective metallic glares, causing excessive manual re-inspection.

Coordination & Action: Coordinated with mechanical engineers to fabricate an ambient optical shroud, realigned coaxial strobed illumination, and adjusted camera exposure trigger timing relative to conveyor encoder pulses.

Verified Outcome

False rejects dropped from 7.8% to 0.4% while maintaining 100% detection of critical surface flaws; net line throughput increased by 11%.

Verified Delivery

Multi-Vendor Assembly Line SAT Dispute Resolution

Context: Multi-station assembly line comprising automated screw-driving, pressing, and robotic transfer built by three separate vendors.

Challenge: Contractors were locked in a finger-pointing dispute over intermittent line halts during dry runs, threatening a milestone penalty.

Coordination & Action: Implemented a 28-point Interface Signal Handshake Matrix and conducted live oscilloscope and PLC signal logging. Isolated a 120ms pneumatic reed switch debounce delay.

Verified Outcome

Adjusted debounce filter logic in PLC and repositioned sensor; 100-cycle continuous dry run completed without fault; SAT signed off in 6 days.

Verified Delivery

Rotary Indexing Table Cycle-Time Bottleneck Shaving

Context: Precision automotive component assembly station on an automated 8-position rotary dial machine.

Challenge: Station was missing client target takt time by 3.1 seconds, throttling total factory output by 250 units per shift.

Coordination & Action: Conducted high-speed video motion study breaking down clamping, processing, inspecting, and unloading. Discovered pneumatic cylinder return strokes were heavily throttled and vacuum release delay was set to 800ms.

Verified Outcome

Tuned pneumatic one-way flow valves and optimized PLC vacuum blow-off pulse to 150ms; saved 2.9 seconds per cycle and achieved target UPH.

Verified Delivery

Manufacturing Equipment Validation (FAT/SAT & IQ/OQ)

Context: Cleanroom medical device sub-assembly automation line subject to stringent qualification audit.

Challenge: Machine builder arrived on site with incomplete qualification documentation and unorganized calibration certificates, delaying line landing.

Coordination & Action: Structured the Validation Master Tracker, audited sensor calibration sheets against standards, and coordinated IQ/OQ parameter logging during 500-unit continuous runs.

Verified Outcome

Compiled complete 80-page validation evidence dossier with photo verification; passed client corporate quality audit on first submission.

Verified Delivery

MES Serialized Traceability Integration

Context: Electronics assembly line linking automated testers with the central plant MES database.

Challenge: High-speed barcode scanners intermittently dropped serial number bindings during rapid index cycles, leading to unverified parts passing downstream.

Coordination & Action: Facilitated a joint workshop between controls programmers and IT database engineers. Standardized bit-level handshake sequence and implemented a buffered retry mechanism in the PLC.

Verified Outcome

Achieved 100% data handshake integrity over a 10,000-part verification run with zero lost barcode records.

Verified Delivery

Robotic Transfer Cell Safety & Handover Coordination

Context: Dual-robot SCARA transfer cell feeding parts from an automated feeder bowl into an ultrasonic welding machine.

Challenge: Safety interlock trips were causing frequent line halts, and operator training materials were non-existent prior to operator handover.

Coordination & Action: Reconfigured optical safety curtain mute zones, mapped robot recovery home sequences, and authored a 6-step visual operator recovery SOP with photo guides.

Verified Outcome

Operator intervention recovery time reduced from 14 minutes to under 90 seconds; smooth operational handover completed.

Integrity Commitment: All outcomes and figures published above are based on actual verified field deployments. Flowtis does not publish invented metrics or proprietary client details.